15 Box Girders in Ramp 1 of Semanggi Interchanges Installed
Reported by Rudi Hermawan | Translated by Maria Inggita
15 box girders that connecting the construction above City inner toll for ramp 1 (Grogol-Blok M lane) in Semanggi Interchanges, South Jakarta, were installed.
From dawn, 2 box girders of S8 and S16 as the 14th and 15th part were installed
City Bina Marga Dept. Head, Yusmada Faizal, said there are 22 segmental box girders for ramp 1. Recently, there are 7 box girders to be installed later.
"From dawn, 2 box girders of S8 and S16 as the 14th and 15th part were installed," he said, Monday (3/6).
Semanggi Interchanges Enters Connecting ProgressHe explained for ramp 1 construction that was started since February 21, is targeted to be done on March 11. Later on, ramp 2 will be done from Cawang or Polda lane to Bundaran Hotel Indonesia.
"The box girder's installation will be finished on 2017, May 6. But the overall project of Semanggi Interchanges is targeted to finish next August," he closed.
For information, there are 295 box girders for Semanggi Interchanges construction. Moreover, there are 219 box girders were installed.
Semanggi Interchanges is budgeted Rp 360 billion. The used budget is from developer compensation for adding building floor coefficient (KLB).